Time and material contracts are typically used for all of the following except ____________.

  1. To augment the project staff
  2. To provide a solution that may not have a fixed price
  3. To begin work before a more formal, long-term agreement can be developed
  4. To acquire experts

 

The correct answer is 2.

A cost plus contract is preferred when providing a solution that may not have a fixed price. Augmenting the project staff, beginning work before a more formal long-term agreement can be developed, and acquiring experts are all reasons for using a time and materials contract.

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading ... Loading ...

Leave your response!

Add your comment below, or trackback from your own site. You can also subscribe to these comments via RSS.

Be nice. Keep it clean. Stay on topic. No spam.

You can use these tags:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

This is a Gravatar-enabled weblog. To get your own globally-recognized-avatar, please register at Gravatar.