In order to meet the planned schedule, the project manager has decided to hire additional staff to work on critical path activities. According to the information recorded on the risk register, hiring the new staff could result in additional training costs for these staff members. What are these training costs an example of?

  1. Secondary risks
  2. Residual risks
  3. Triggers
  4. Reserve analysis

The correct answer is 1.

Hiring the additional staff is the risk response plan; paying for their training is the new risk created by the response plan. If new staff is not hired, then there will be no additional cost for training.

Related Resources
PMP Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading ... Loading ...

Leave your response!

Add your comment below, or trackback from your own site. You can also subscribe to these comments via RSS.

Be nice. Keep it clean. Stay on topic. No spam.

You can use these tags:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

This is a Gravatar-enabled weblog. To get your own globally-recognized-avatar, please register at Gravatar.