PMP Exam Prep Question of the Week
Author: Guest Authors
23 October 2012
455 views
No Comments
In order to meet the planned schedule, the project manager has decided to hire additional staff to work on critical path activities. According to the information recorded on the risk register, hiring the new staff could result in additional training costs for these staff members. What are these training costs an example of?
- Secondary risks
- Residual risks
- Triggers
- Reserve analysis
The correct answer is 1.
Hiring the additional staff is the risk response plan; paying for their training is the new risk created by the response plan. If new staff is not hired, then there will be no additional cost for training.
Related Resources
PMP Mobile App
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Weekly Question Series
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week







Leave your response!