You have just compiled a short list of qualified sellers based upon preliminary proposals. Which process are you performing?

  1. Plan Procurements
  2. Conduct Procurement
  3. Administer Procurements
  4. Close Procurements

 

The correct answer is 1.

The qualified seller list is an output of Plan Procurements. It is an input to Conduct procurement, which occurs before answers Administer and Close Procurements.

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading ... Loading ...

Leave your response!

Add your comment below, or trackback from your own site. You can also subscribe to these comments via RSS.

Be nice. Keep it clean. Stay on topic. No spam.

You can use these tags:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

This is a Gravatar-enabled weblog. To get your own globally-recognized-avatar, please register at Gravatar.