Who is responsible for providing the financial resources for the project?
- The customer
- Sponsor (can also be the customer)
- Project manager
- Functional Manager
The answer is 2.
The customer is the entity paying for the project, while the sponsor is responsible for releasing the “working budget” for the project. The “working budget” is what is being described by the term “financial resources” in the question. Keep in mind that the sponsor on an internal project can also be the customer.
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Weekly Question Series
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week






Leave your response!